Construction of Ķekava primary school, stage III, infrastructure works
Customer
Contractor
Designer
Object type
Address
Year of commissioning
Construction status
The following works are performed, during the project:
Building out of engineering communications:
Household sewage: 74 m
Rainwater sewage: 581 m
Rainwater sewage treatment plants: Q=15 l/s
Draining networks: 129 m
Heating main: 40 m
Protection of existing VS 20kV cables: 156 m
Territory power and lighting networks: 1165 m
External low-voltage networks (cable sewage): 300 m
Works on building out of roads and squares were performed and the territory was improved including planting of greenery (trees and decorative shrubs). Small architectural and territory improvement elements – benches, waste-bins, bicycle stands, sports inventory – were installed.
Paved squares – 1007 m2
Paved pavements – 1665 m2
Asphalted squares – 1502 m2
Sports grounds with rubber surfacing – 700 m2
Greenery – 3481 m2